This Project has been completed 2017

Construction is planned to resume in mid-April 2017 at the Johns Road and Klatt Road intersection. There will be new traffic patterns similar to last year with traffic shifting to the north on Klatt Road, flagging operations, and lane restrictions. The extended 21-day closure of the Johns Road and Klatt Road intersection is being planned for May 2017.  We are currently working with the contractor, municipality, and school district to finalize the closure dates.  Project completion is anticipated to occur by June 30, 2017. 

 

Visit http://www.alaskanavigator.org/ for project updates and information or contact the Project Engineer, Steve Reed, at 907-720-9810.

 

 